FLY ASH DISPOSAL AREA

SITE DESCRIPTION

In operation from the 1940’s to the 1950’s, this area was used for disposal of fly ash, residual coal, clinkers, and other residue from the coal-fired power plant and is nearly 5 acres in size. The site is abandoned and covered with natural vegetation, but has no soil or clay cover.

The PA/SI was completed in 1991, the RI was completed in May 1996; sampling found no significant contamination. 

This site is considered Response Complete and requires no further action under the IRP per the Jaycor RI.  USACHPPM Phase II complete.

This site may need to be reopened for additional sampling to support the no further action determination.

 


    